Tuesday, June 14, 2011

A Summer of Remodeling: June 5-11

Completed Projects Update: Week 2

* re-texture all of the ceilings (from popcorn to a flat finish)
Sunday: after a week of getting bids, we find our winner!
Monday: all ceilings scraped
Tuesday: all ceilings newly floated
Wednesday: ceilings sanded and floated
Thursday/Friday: ceilings sanded and flat finish applied
Saturday: ceilings painted & finished beautifully
If you are planning to refinish your ceilings, we recommend the team that did ours!!


* change all linoleum to tile (kitchen and both bathrooms)
All linoleum is removed and tile has been purchased
Wednesday: baseboards are removed to prep for tile laying
Thursday: David's family is coming in town to help lay tile :)


KITCHEN

Friday: David and his dad, Jim, decided on a pattern and dry laid the tile in kitchen


Saturday: David and Jim started setting tiles; little did we know when we started this process how laborious setting travertine can be... it requires a few more steps than setting ceramic tile and took about twice as long
David using wet saw for kitchen tiles.

If you are in the Austin area, we highly recommend the place we used to rent this saw. Let us know and we will refer you to them :)
they worked sooooo hard
David and his dad, Jim


MASTER BATH

Saturday: David and Jim took at break from kitchen to set tiles in master bath; project moved along quickly

MASTER VANITY



* remove wood paneling in entry and family room
Done!

* re-texture paneled walls
Wednesday: process started on paneled walls; walls have been taped and floated
* update kitchen

FIXTURES
Tuesday: selected faucet-- now trying to decide between chrome and bronze finish.


Wednesday: We ordered a bronze Delta faucet and choose the cabinet door pulls and knobs





COUNTERS
Tuesday: changed counter top selection and then purchased counters and under-mount sink!

New selection-- I stumbled upon it and like it more than our first choice!
In fact, its just what I was hoping to find originally!!!


CABINETS

Saturday: We've found the person to hire to paint the cabinets; he starts on Monday :)

* update bathrooms
Tuesday: new toilets selected and ordered
Friday: David applied waterproofing to master shower walls
Saturday: laid ceramic tile in master bath and vanity

* paint walls and trim throughout house
Wednesday: I am heading to Home Depot to start looking for colors!
Wednesday: hired a painter for ceilings; will commence this weekend

* add a privacy fence to the west side of property
no progress yet

* clean-up landscaping in front and back yard
Monday: found a garden center with great options on perennials that we can plant this month.

* miscellaneous
Tuesday: took some necessities over to the house :)

* purchase/make window treatments

Wednesday: shopped for drapery
; decided on fabric for baby's room drapes

The plan is to make drapes from this fabric and a cream colored roman shade.

This will pair nicely with the yellow gingham bed linens, white Jenny Lind crib, and white shelving unit!